| Task | Depends On | Blocks | Risk if Delayed | Buffer |
|---|---|---|---|---|
| Production order placed | PP sample approved | Factory timeline, launch date, photography, influencer seeding | Every week of delay = 1 week later launch date. No workaround. | Build 3-week buffer in PP sample round |
| BIS licence received | Test samples submitted + lab testing complete | Myntra listing, any regulated marketplace, ISI mark on product label | Myntra launch delayed by weeks-months. D2C unaffected. | Submit in Week 1. Accept BIS delays in Myntra planning (Month 8 not Month 7). |
| Product photography | PP or production sample in hand — not proto | Product reveal content, Myntra catalogue, D2C product page images | Cannot publish product reveal or populate D2C site without real product photos. | Schedule shoot for Week 1 after PP approved. Don't wait for production pairs. |
| Influencer seed boxes shipped | Production pairs received + QC passed | Influencer Reels, pre-launch content wave, social proof before launch | Fewer pre-launch Reels = lower Day 1 awareness. CAC spikes. | Reserve 20 pairs from production for seeding before listing any for sale. |
| Shopify site (product page) live | Photography complete + brand identity locked | Influencer CTA destination, paid ads landing page, Myntra redirect target | Influencer Reels have no destination to drive traffic to. Wasted reach. | Build site in Month 3 on placeholder images — swap photography in Month 5. |
| Trademark TM-A filed | Brand name + emblem finalised | Legal right to use ™ symbol. Without filing, name is unprotected. | Someone else files "RouCN" first. Expensive legal dispute. | File Week 1 — before any public brand launch. Takes 1 day online. |
| Myntra catalogue submission | BIS licence + product photography + GST registration | Myntra listing approval (4–6 week review process) | Myntra launch delayed beyond Month 8. Small impact — D2C is primary. | Submit to Myntra in Month 7. Accept Month 8 live date. |
| Klaviyo email flows active | Email list exists + Shopify integration set up | Waitlist conversion, post-purchase NPS, Day 14 review request, referral prompt | Missed touchpoints in critical post-purchase window = lower RPR. | Set up flows in Month 3 on dummy data. Test thoroughly in Month 6. |
| Packaging print order delivered | Packaging design finalised + printer briefed | Packing production pairs + influencer seed boxes | Shoes arrive but cannot be boxed. Launch delayed by packaging lead time. | Order packaging in Month 3, 6-week lead. Arrives before production shoes. |
First-time founders consistently underestimate BIS certification timeline, assuming 4–6 weeks when the actual average is 3–5 months. This single miscalculation delays Myntra onboarding by months — which is why RouCN's roadmap starts BIS in Month 0 (not Month 3) and treats Myntra as a Month 8 activation, not a launch-day channel. D2C is designed to be fully functional without BIS, allowing a legal launch while the certification completes.
Day 30 is too early — too much noise, not enough signal. Day 90 is too late — if the model is broken, you've burned through budget waiting to confirm it. Day 60 is the moment when the founder has enough data (sell-through trend, CAC reality, channel mix performance, first reviews) to make a truly informed decision about whether to scale, adjust, or stop. RouCN's founder must treat the D+60 gate as a Board Meeting — with data, not gut feel, driving the outcome.