🦝 RouCN · PM Case Study
Roadmap
12-MONTH PLAN · CRITICAL PATH · GO/NO-GO GATES
06 / 07 ← Block 05: GTM
Block 07: Measurement →
6.1 Phased Roadmap — Month 0 to 12
6.2 Critical Path & Dependencies
6.3 Go/No-Go Criteria — Day 30, 60, 90
6.1
Phase 0 — M0–M2
Foundation
Phase 1 — M3–M4
Build
Phase 2 — M5–M6
Pre-Launch
Phase 3 — M7
Launch
Phase 4 — M8–M10
Scale
Phase 5 — M11–M12
Consolidate
M0
Register / BIS start
M1
Factory + proto
M2
Fit sample + brand
M3
PP approved + site live
M4
Production order placed
M5
Pre-launch content
M6
Influencer seeding
M7
🚀 DROP 001
M8
Myntra live
M9
Batch 2 ships
M10
RPR target hit
M11–12
SKU 2 brief + Y2 plan
Phase 0 · Month 0–2
Foundation — Build Everything Before Anyone Sees It
Legal, factory, brand, BIS. The unsexy work that everything else depends on.
0
May 2026
Ignition
Build
GST registration + current account opened
Trademark TM-A filed (Class 25 + 35)
BIS IS 17043 application submitted to empanelled lab
Business entity registered (Sole Prop or OPC)
Domain roucn.in secured + Shopify account opened
Measure
All registrations have confirmation receipts
Month progress
1
Jun 2026
Factory & Brand
Build
Factory shortlist + physical visits to top 3 Agra factories
Tech pack sent to 2 factories — proto samples commissioned
Brand identity finalised: logo, raccoon emblem, color palette
SKU naming convention locked (RCN–001–NR/BB/SF)
Packaging design brief sent to printer
Measure
2 factories confirmed for proto commissioning
Brand identity signed off — no more changes after this
Month progress
2
Jul 2026
Proto & Fit
Build
Proto samples received from both factories — side-by-side review
Factory 1 selected — NDA + manufacturing agreement signed
Fit sample commissioned with corrections from proto
Shopify waitlist landing page live (email capture only)
Instagram page launched — raccoon emblem reveal post
Measure
Instagram: 500 followers by Month 2 close
Email waitlist: 50+ signups
Proto quality: passes basic spec check (no disqualifiers)
Month progress
Phase 1 · Month 3–4
Build — Product Approved, Brand Established, Site Ready
PP sample approved. Production order placed. Photography begins. Waitlist grows.
🏁 MILESTONE
3
Aug 2026
PP Approved
Build
Fit sample wear-tested on 5 real people across sizes
PP sample corrections briefed — PP sample commissioned
BIS test samples submitted to lab (parallel with sampling)
Packaging print order placed with confirmed spec
D2C Shopify site fully built — product page, size guide, policy pages
Ship
Shopify site soft-live (accessible via link, not promoted)
Measure
PP sample quality: ≥85% spec accuracy
Instagram: 1,500 followers | Email: 300 signups
BIS lab test: in progress, no failures reported
Gate: PP approved = proceed to production order
🏁 MILESTONE
4
Sep 2026
Production Order
Build
PP sample approved — production order placed (100 pairs, 50% deposit)
Product photography scheduled for Week 3 (shoes arrive as pre-prod samples)
Influencer outreach begins — DMs sent to 30 target creators
Mid-production QC checkpoint scheduled for Week 6 of production
Ship
Production order placed — factory clock starts
First 3 BTS Reels published (factory visit, sampling journey)
Measure
10+ influencer yeses confirmed for seeding
Instagram: 2,000 followers | Email: 500 signups
Gate: Production order placed = launch clock starts
Phase 2 · Month 5–6
Pre-Launch — The Buildup Is the Brand
Photography, content machine, influencer seeds, waitlist surge. Shoes in transit.
5
Oct 2026
Content Machine
Build
Product photography shoot — all 3 colorways, lifestyle + product
Hero Reel: Noir Chrome full reveal
Influencer seed boxes prepared — 20 boxes packed + shipped
Myntra seller application submitted
PR kit sent to 5 lifestyle/fashion journalists
Ship
Noir Chrome Reel published — first product reveal
Bandit Bone teaser Story published
Price revealed: ₹3,499. Launch date: "Nov 2026."
Measure
Instagram: 3,000 followers | Email: 700 signups
Noir Chrome Reel: target 15K+ views
Mid-production QC: pass (no batch issues)
Content library built: 30+ pieces ready for launch month
6
Nov 2026
Final Countdown
Build
Shoes arrive from factory — final 100% QC inspection
Pack + box all 85 listed pairs — ready to ship
Klaviyo email flows tested end-to-end (waitlist → launch → post-purchase)
Shopify checkout stress tested — dummy orders placed + refunded
Launch date locked: first week of Dec 2026
Ship
Survivor Forest colorway reveal + launch date announcement
Influencer unboxings begin (Wave 1 — 5 creators go live)
Waitlist: 48-hour early access email sent with PACK10
Measure
Instagram: 4,000+ followers | Email: 900+ signups
3 influencer Reels with 10K+ views before launch day
QC pass rate: 97%+ (≤3 defective pairs from 100)
Gate: QC pass + 3 viral Reels = green light for launch
Phase 3 · Month 7
🚀 Launch — Drop 001 Goes Live
Dec 2026. 85 pairs. The raccoon is out.
7
Dec 2026
DROP 001 🚀
Week 1 — Launch
D2C live — 8 AM. Waitlist email blast.
Instagram launch post + hour-by-hour Stories
Influencer Wave 1 (5 creators) — 10 AM
Influencer Wave 2 (10 creators) — Day 3
Macro influencer Reel — Day 3 afternoon
Week 2–3 — Momentum
Daily sell-through Story updates
Customer review request emails go out
SF colorway sold out Story (if achieved)
First 5 customer photos reshared
Reorder trigger check at 20 pairs remaining
Month 7 Targets
50+ orders in first 30 days
SF sold out within 72 hrs of launch
Product rating ≥ 4.2★ on first 20 reviews
Instagram: 5,000 followers
CAC ≤ ₹800 blended
Return rate < 12%
Phase 4 · Month 8–10
Scale — Second Channel, Second Batch, First Repeat Purchases
Myntra live. Batch 2 ships. NSM target in sight. Community activates.
🏁 MILESTONE
8
Jan 2027
Myntra Live
Build
Myntra listing live — BIS cert received (gate cleared)
Batch 2 production order placed (200 pairs)
Post-purchase email flows fully active (NPS Day 7, review Day 14)
Ship
Myntra product listing live with approved catalogue
Batch 2 order confirmed: colorway split adjusted from B1 data
Measure
Cumulative 80+ pairs sold (D2C + Myntra)
First 10 Myntra orders fulfilled
NPS score from first cohort: target ≥ 35
9
Feb 2027
Batch 2 Ships
Build
Batch 2 arrives — QC + pack — listed on D2C + Myntra
WhatsApp inner circle launched (invite repeat buyers)
Referral program activated via ReferralCandy
Ship
Batch 2 live — "Drop 001.2 — more pairs, same energy"
WhatsApp: first exclusive preview sent to inner circle
Measure
Cumulative 140+ pairs sold
Email list: 1,000+ subscribers
First referral orders tracking
🏁 NSM TARGET
10
Mar 2027
RPR Target Hit
Build
90-day RPR measurement window closes (Dec buyers → Mar reorders)
Silhouette 002 brief written based on B1+B2 data
Amazon India seller account initiated
Ship
Silhouette 002 concept teaser (BTS of brief writing)
OG 100 anniversary email to first buyers ("3 months in")
Measure
NSM: RPR @ 90 days ≥ 15% ← THE MOMENT
Total revenue: ₹4.9L+ (base case)
Instagram: 8,000+ followers
Phase 5 · Month 11–12
Consolidate — Learn, Document, Plan Year 2
Full year debrief. SKU 2 brief finalised. Year 2 roadmap begins.
11
Apr 2027
Learn
Build
Full sell-through analysis: colorway, size, city, channel
NPS survey run across 100+ customers
5 customer interviews — what's working, what's missing
Amazon India listing live (Year 2 volume channel)
Measure
NPS ≥ 40 target
Return reason codes: top 3 identified + resolved
Budget vs actuals: every line item reviewed
12
May 2027
Year 2 Brief
Build
Silhouette 002 tech pack initiated (Mid-Top canvas)
Pop-up event feasibility decision made (Tier 1 city)
Year 2 OKRs written: ₹1–2 Cr ARR target
First investor/accelerator outreach if RPR + revenue targets met
Measure
Year 1 total revenue vs scenario forecast (bear/base/bull)
Community size: 10K+ IG | 1,000+ email | 200+ WhatsApp
Unit economics: GM% per pair improving with scale?
6.2
⛓️
Critical path logic: The longest chain of dependent tasks determines the earliest possible launch date. There are three independent chains running in parallel — product (factory → sampling → production → QC → launch), compliance (BIS application → testing → mark), and brand (identity → site → content → influencer). All three must converge before Drop 001 goes live. A delay in any single critical chain delays everything downstream.
🔴 Chain 1 — Product (Critical — Longest Path)
Factory Selection
Physical visits + proto commission
Weeks 1–4
Blocks: everything below
Proto Sample
Receive + review + corrections
Weeks 3–6
Blocks: fit sample
Fit Sample
Wear test on real feet
Weeks 6–9
Blocks: PP sample + photography
PP Sample Approval
Final sign-off before production
Weeks 9–12
Blocks: production order
Production (100 pairs)
45–60 day factory cycle
Weeks 12–20
Blocks: QC → pack → launch
🟠 Chain 2 — Compliance (Important — Must Complete Before Myntra)
BIS Application
Submit IS 17043 application to empanelled lab
Week 1 — Start immediately
Blocks: ISI mark on product
Lab Testing
Submit 6–10 samples from fit/PP stage
Weeks 8–16 (parallel)
Blocks: BIS licence
BIS Licence Granted
ISI mark authorised
~Week 20–24
Blocks: Myntra listing (mandatory)
Myntra Onboarding
Submit brand + BIS docs to Myntra seller portal
Month 7–8
Blocks: Myntra sales
Myntra Live
First listing approved + live
Month 8
Blocks: marketplace revenue
🟡 Chain 3 — Brand & Marketing (Important — Must Complete Before Launch)
Brand Identity Locked
Logo, mascot, palette, SKU naming
Month 1
Blocks: all downstream brand work
Shopify Site Live
Waitlist page → full product site
Month 2 (waitlist) → Month 3 (full)
Blocks: influencer CTA + email capture
Photography
Requires PP sample or production sample
Month 4–5 (needs PP sample)
Blocks: product reveal content
Influencer Seeding
Requires production pairs in hand
Month 6 (needs production shoes)
Blocks: pre-launch Reels
Launch Countdown
8-week content machine live
Month 5–6
Blocks: Day 1 demand
Complete Dependency Register — Every Hard Block
TaskDepends OnBlocksRisk if DelayedBuffer
Production order placed PP sample approved Factory timeline, launch date, photography, influencer seeding Every week of delay = 1 week later launch date. No workaround. Build 3-week buffer in PP sample round
BIS licence received Test samples submitted + lab testing complete Myntra listing, any regulated marketplace, ISI mark on product label Myntra launch delayed by weeks-months. D2C unaffected. Submit in Week 1. Accept BIS delays in Myntra planning (Month 8 not Month 7).
Product photography PP or production sample in hand — not proto Product reveal content, Myntra catalogue, D2C product page images Cannot publish product reveal or populate D2C site without real product photos. Schedule shoot for Week 1 after PP approved. Don't wait for production pairs.
Influencer seed boxes shipped Production pairs received + QC passed Influencer Reels, pre-launch content wave, social proof before launch Fewer pre-launch Reels = lower Day 1 awareness. CAC spikes. Reserve 20 pairs from production for seeding before listing any for sale.
Shopify site (product page) live Photography complete + brand identity locked Influencer CTA destination, paid ads landing page, Myntra redirect target Influencer Reels have no destination to drive traffic to. Wasted reach. Build site in Month 3 on placeholder images — swap photography in Month 5.
Trademark TM-A filed Brand name + emblem finalised Legal right to use ™ symbol. Without filing, name is unprotected. Someone else files "RouCN" first. Expensive legal dispute. File Week 1 — before any public brand launch. Takes 1 day online.
Myntra catalogue submission BIS licence + product photography + GST registration Myntra listing approval (4–6 week review process) Myntra launch delayed beyond Month 8. Small impact — D2C is primary. Submit to Myntra in Month 7. Accept Month 8 live date.
Klaviyo email flows active Email list exists + Shopify integration set up Waitlist conversion, post-purchase NPS, Day 14 review request, referral prompt Missed touchpoints in critical post-purchase window = lower RPR. Set up flows in Month 3 on dummy data. Test thoroughly in Month 6.
Packaging print order delivered Packaging design finalised + printer briefed Packing production pairs + influencer seed boxes Shoes arrive but cannot be boxed. Launch delayed by packaging lead time. Order packaging in Month 3, 6-week lead. Arrives before production shoes.
🔬 PM Hypothesis H16 — The BIS Timeline is the Most Mis-Estimated Dependency

First-time founders consistently underestimate BIS certification timeline, assuming 4–6 weeks when the actual average is 3–5 months. This single miscalculation delays Myntra onboarding by months — which is why RouCN's roadmap starts BIS in Month 0 (not Month 3) and treats Myntra as a Month 8 activation, not a launch-day channel. D2C is designed to be fully functional without BIS, allowing a legal launch while the certification completes.

Evidence: BIS QCO 2024 compliance reports from multiple D2C founders consistently cite certification timelines of 90–150 days including testing rounds. DPIIT BIS portal processing adds 4–8 weeks after lab test submission. (DPIIT footwear compliance guidance 2024)
6.3
🎯
Why define these now: In the moment of slow sales, every founder rationalises. "It's just slow because of the season." "People will order after payday." Pre-defined thresholds remove the emotional variable. If the number says pivot, you pivot — not because you're panicking, but because you agreed in advance that this is what the data means. The gates are a pre-commitment device.
D+30
First Signal Gate
30 days post-launch. Is the demand real?
✅ GO — Double Down
≥25 orders | Rating ≥4.2★ | Return rate <10%
Proceed with Batch 2 planning. Activate Myntra onboarding. Increase influencer seeding budget. Business model is working.
⚠️ PIVOT — Diagnose & Adjust
10–24 orders | Rating 3.8–4.2★ | Return rate 10–15%
Do NOT place Batch 2 yet. Run 10 customer interviews this week. Activate ₹40K paid ads test. Identify whether issue is awareness (low site traffic) or conversion (high traffic, low purchase). Fix the weaker link.
🛑 STOP — Root Cause First
<10 orders | Rating <3.8★ | Return rate >15%
Halt all marketing spend. Do not place Batch 2. Pull 5 returned pairs, inspect defects. Interview every customer who ordered. Either quality is broken or price is wrong or trust is absent. Find which one before spending another rupee.
D+60
Scale Gate
60 days post-launch. Is it repeatable?
✅ GO — Scale
≥55 cumulative orders | Batch 2 in transit | CAC ≤₹800
Myntra listing live or in final review. Email list ≥700. Referral program active. Plan Batch 3 brief. First paid ads test (₹20K) with conversion data to optimise against.
⚠️ PIVOT — Channel Mix
30–54 cumulative orders | CAC ₹800–1,200
Review channel split: is D2C underperforming vs Myntra? If Myntra is converting better, shift stock allocation toward marketplace. If D2C is dead (low traffic), organic strategy is not working — activate paid at ₹20K/month test. Don't change the product, change the acquisition channel.
🛑 STOP — Reframe
<30 cumulative orders | CAC >₹1,500 | Rating declining
Product-channel fit has not been established. Pause Batch 2. Consider: Is the price wrong? Is the silhouette wrong for this customer? Is the positioning unclear? Run 20 customer interviews. If quality is the issue, go back to factory. If positioning is the issue, pivot the story — not the shoe.
D+90
NSM Gate
90 days post-launch. Is the brand sticky?
✅ GO — Year 2 Mode
RPR ≥15% | ≥80 cumulative orders | NPS ≥35
NSM target hit. Product-market fit confirmed. Begin Year 2 planning: SKU 002 brief finalised, pop-up feasibility, first investor/accelerator outreach, Amazon India. RouCN is a real brand.
⚠️ PIVOT — Retention Fix
RPR 8–14% | 50–79 cumulative orders | NPS 25–35
Demand exists, retention is below target. Audit post-purchase experience: are emails landing? Are customers being invited into community? Is the WhatsApp inner circle active? RPR is a lagging indicator of experience quality — fix the experience to fix the metric. Push community harder: IGCF, referral, WhatsApp invite.
🛑 STOP — Strategic Review
RPR <8% | <50 cumulative orders | NPS <25
3 months post-launch with RPR below 8% and NPS below 25 means the product or the brand is not resonating deeply enough for a D2C brand to sustain. Strategic review: Is this a product problem (wrong silhouette, wrong price)? A story problem (narrative not landing)? A market timing problem? Make a decision within 30 days: pivot the product, pivot the positioning, or pause and rebuild before spending more.
Go/No-Go Summary — All Metrics at a Glance
RouCN · Decision Gate Dashboard
Metric
✅ GO (Double Down)
⚠️ PIVOT (Diagnose)
🛑 STOP (Root Cause)
Orders D+30
≥25 orders
10–24 orders
<10 orders
Orders D+60
≥55 cumulative
30–54 cumulative
<30 cumulative
Orders D+90
≥80 cumulative
50–79 cumulative
<50 cumulative
Product Rating
≥4.2★
3.8–4.2★
<3.8★
Return Rate
<10%
10–15%
>15%
CAC (blended)
≤₹800
₹800–1,200
>₹1,500
RPR @ D+90
≥15%
8–14%
<8%
NPS @ D+90
≥35
25–35
<25
Gross Margin
≥55% D2C
45–55%
<45% (guardrail breach)
🔬 PM Hypothesis H17 — The D+60 Gate is the Most Important Decision Point

Day 30 is too early — too much noise, not enough signal. Day 90 is too late — if the model is broken, you've burned through budget waiting to confirm it. Day 60 is the moment when the founder has enough data (sell-through trend, CAC reality, channel mix performance, first reviews) to make a truly informed decision about whether to scale, adjust, or stop. RouCN's founder must treat the D+60 gate as a Board Meeting — with data, not gut feel, driving the outcome.

Evidence: Standard D2C brand assessment frameworks (YC, a16z consumer playbook) recommend a 60-day post-launch cohort review as the minimum viable data window for a first drop. 30 days has too much launch-week noise; 90 days has too much sunk cost to pivot cleanly.
RouCN · PM Path · 06 of 07
🦝
Next → 07 Measurement Iteration